The Electricity Company of Ghana (ECG) has announced a three-day planned power outage in parts of the Ashanti Region to allow the Ghana Grid Company (GRIDCo) to upgrade a major transmission line.
The outage will run from Sunday, 22 November to Tuesday, 24 November 2026, from 7:30am to 5:00pm each day, ECG said in a notice issued on Saturday, 21 November.
The shutdown is to enable GRIDCo to continue the ongoing upgrade of the Anwomaso to Ridge Bulk Supply Point transmission line.
The project involves replacing the existing 364MVA single-circuit transmission line with a modern double-circuit transmission line rated at 2 x 488MVA — a total of 976MVA.
ECG said the work forms part of ongoing efforts to improve power supply in the Ashanti Region.
Areas to be affected
Guinness Ghana Limited, Fan Milk, parts of Kaase, Bomplex, Abattoir, Georgia Hotel, Atonsu Kuwait, Naachia, Sawuah, Aprabon, Adagya, Esereso, Feyiase, Zoomlion and surrounding areas.
“The inconvenience caused to affected customers is deeply regretted,” ECG said.
The company urged customers in the affected areas to take note and plan accordingly for the three-day interruption.