You are here: HomeNewsHealth2015 05 18Article 358649

Health News of Monday, 18 May 2015

Source: GNA

Euroget's hospital project behind schedule

Motivated by the desire to improve upon the health needs of Ghanaians, Government engaged Euroget, an Egyptian project management and financial group, to deliver nine hospitals nationwide, at a cost of $ 686 million.

Steven Gamble, Lead partner at Norton Rose Fulbright, a global legal practice that provides the world’s pre-eminent corporations and financial institutions with a full business law service, described the Euroget De-Invest (EDI) and GoG (Government of Ghana) Hospitals project as “the African PPP (Public, Private, Partnership) of the Year”.

“Norton Rose Fulbright advised Absa/Barclays Group in relation to the Republic of Ghana’s $ 686 sovereign promissory note programme for the financing of the construction of seven civilian and military hospitals by Euroget De-Invest SA in Ghana.

“The project involved back- to-back European and South African listings of the sovereign note issuance.”

In April 2008 EDI signed a memorandum of understanding with Ghana represented by the Ministry of Health (MOH) and the Ministry of Defence to design, engineer, construct and equip nine hospitals with a total capacity of 1,310 beds.

The projects comprise one military hospital in Kumasi, one regional hospital in Wa and another one in Kumasi and district hospitals for Salaga, Nsawkaw, Tepa, Konongo, Twifo Praso and Madina

According the Euroget website, the construction and installation of medical equipment of all the hospitals are expected to be completed within 48 months.

As part of the project, Euroget engaged the services of a number of consultants and contractors to build these hospitals.

The flagship hospital projects, which commenced with a ground breaking ceremony in Wa for a 160- bed capacity Upper West Regional Hospital, was done in 2010 by President John Dramani Mahama, then Vice President and was expected to be completed in 24 months.

A visit to the project site by Ghana News Agency (GNA) showed that the project has come to a halt.

Financial constraints and lack of materials accounted for the stoppage of work on the project, a former worker told the GNA on condition of anonymity.

The project area has been barricaded with roofing sheets, and the site secured.

In a related development works on the first phase of the 60-bed Tepa District Hospital project would be completed, Mr Jonathan Tagbo, the Project Site Engineer, has disclosed.

“Greater percentage of civil works has been executed and we are left with the finishing touches,” he told GNA after a tour of the project site at Tepa in the Ahafo-North District to inspect the progress of work.

Works done so far, include the construction of an administration block, staff housing units, Out-Patient-Department, pharmacy block, market and a security post.

Mr Tagbo said the coming days would see the contractors, EDI, commence electrical and plumbing works, roofing, internal plastering and external drainage system.

Actual works on the Tepa project, according to the contractors began two years ago.

Mr David Brown an Engineer of Euroget, told the GNA that with the first phase coming to an end, the contractors anticipate to work around the clock to complete the second phase in 2016, and subsequently do the handing-over to the MOH.

Mr Khalid Hamed an Official of Euroget, told the GNA that China Railways, a Chinese construction firm, has been sub-contracted to support construction works with the objective to finish the work as scheduled.

Mr Adu Gyamfi of the MOH, told the GNA that he was satisfied with the progress of work so far done at Tepa and that the Ministry had stepped up efforts to get the projects to be completed on time to enhance healthcare delivery.

Meanwhile, construction works is yet to start on the proposed regional hospital, which was supposed to have been given out on contract in 2014.

When GNA visited the project site at Sewua, for instance, the construction works has not started, however, Top International Ghana Limited, a construction firm sub-contracted was on site, making preparations to commence work.

Mr Liang Baoshang the Project Manager, told the GNA that all the designs, engineering and specifications have been completed.

“We have few outstanding issues to sort out with government, bothering on the release of funds,” he revealed.

“Our equipment is all intact and we hope to start working on the project as soon as possible,” Mr Baoshang said.

When contacted, Dr Alexis Nang-Beifubah Ashanti Regional Director of Health, declined to comment, on the project, saying the MOH is in-charge of affairs.

Some local residents who spoke to the GNA expressed worry at the seemingly delay in completing the facility, urging the government to demonstrate its commitment to execute the project.

Mr Akwasi Agyemang-Osei, former Assemblyman for Prabon, one of the beneficiary communities, expressed worry about the delay in putting up the project, and appealed to the authorities to work assiduously to complete it on time.

“We are always found wanting in times of emergencies. Government should, therefore, do what is expected of it to help alleviate the plight of the people,” he added.

At Nsawkaw the capital of Tain District in the Brong- Ahafo Region and a beneficiary of the Euroget project, the site Engineer referred to as Zaid said he could not comment on the progress of work though workers were on site.

The project is being undertaken by David Walter Limited, General building contractors and Civil Engineers.

Mr J. Adu-Koranteng, Tain District Co-ordinating Director in an interview said work on the project is progressing steadily.

At Salaga in the East Gonja District the Engineering Regiment of Ghana Armed Forces is preparing to complete the project, which is being undertaken by Maico Limited.

Mr Mohammed Aminu Lukumanu, District Chief Executive told the GNA that the project would be completed in the next nine months.

He said the project was halted during the last Christmas festivities and upon enquires the contractor complained about the difficult terms of the project.

Works at Madina, Twifo Praso and Konongo hospitals are yet to commence.